murchr wrote:guru267 wrote:murchr wrote:“Three heavy fuel oil thermal plants around Nairobi totalling 280MW have signed PPAs (power purchase agreements) with Kenya Power with the same structure and received the World Bank guarantee earlier this year,”
And the likes of VVS still think that the WB is doing this for them.
This kind of reasoning stresses me!!
Are you aware how many transmission lines are available
AROUND NAIROBI as opposed to
TURKANA?? ?
Guru where is Turkwel? Surely how long can it take to connect to Turkwel. Please stop thinking small. Nairobians are not the only consumers of Power.
The point is that there are transmissions lines available for use around Nairobi
today as opposed to turkana where they are being
built from scratch!The wind farm will be completed before the transmission lines are finished while the thermal power is being built around transmission lines!!
i hope this is not rocket science!!
This means the WB is backing thermal power that will actually be sold and abandoning wind power that will be wasted because of no lines!!