youcan'tstopusnow wrote:mwekez@ji wrote:Kumbe even this counter has a “Good-to-Great” Strategy (launched in 2008)
How have they done on the milestones?
Currently, G2G strategy key target is bring onboard 3,000 more Megawatts by 2018.
The progress has been as follows;
2008 they had installed capacity of 1,006 MW
2009; 1,018 MW
2010; 1,057 MW
2011; 1,147 MW
2012; 1,231 MW
2013; 1,712 MW ¿¿¿
2014; ???
2015; ???
2016; ???
2017; ???
... target by 2018; 5,000 MW