From the notes on the financial performance;the company is on gear to implement other Horizon II projects which include 350mw of geothermal projects comprising;
70MW Olkaria I Unit 6
140MW Olkaria V
140MW Olkaria VI
From the news they have been sharing Kengen is short by 8.2bn for funding of Olkaria I unit 6.This money they will get from borrowing and most likely JICA will give them the money.
The ksh.50bn rights issue money will be for implementing 140MW Olkaria V and 140MW Olkaria VI and the remaining balance for the project will be borrowing.