Ericsson wrote:Kipevu I thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid
I don't think so. Kipevu 1 has a PPA until 2023. Olkaria V is has come in half, the other half in November 2019. One plant can not retire another one, they have separate tariffs, separate contracts. Early retirement is only possible if they pay off KenGen for the duration to PPA expiry