#161 Posted : Tuesday, September 17, 2019 10:09:26 AM
Rank: Member


Joined: 11/17/2018
Posts: 173
Location: Mars
1,010,300 shares on Board at Sh5.54

http://www.nutcracker.af.../NSE.EQ.KEGN.O0000/quote
Ericsson
#162 Posted : Wednesday, September 18, 2019 12:40:17 AM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
Kipevu I thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
VituVingiSana
#163 Posted : Wednesday, September 18, 2019 3:00:49 AM
Rank: Chief


Joined: 1/3/2007
Posts: 18,103
Location: Nairobi
Ericsson wrote:
Kipevu II thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid
The relief on our bills will be welcome. Hopefully there is some relief.
Greedy when others are fearful. Very fearful when others are greedy - to paraphrase Warren Buffett
Ericsson
#164 Posted : Wednesday, September 18, 2019 11:40:57 AM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
[quote=Extraterrestrial]1,010,300 shares on Board at Sh5.54

http://www.nutcracker.af...NSE.EQ.KEGN.O0000/quote[/quote]
Alot of shareholders re-alignment taking place in this counter going by the volumes being traded.
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Extraterrestrial
#165 Posted : Wednesday, September 18, 2019 12:05:20 PM
Rank: Member


Joined: 11/17/2018
Posts: 173
Location: Mars
Ericsson wrote:
Kipevu II thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid


Interesting. Source?
Extraterrestrial
#166 Posted : Wednesday, September 18, 2019 12:06:59 PM
Rank: Member


Joined: 11/17/2018
Posts: 173
Location: Mars
Ericsson wrote:
[quote=Extraterrestrial]1,010,300 shares on Board at Sh5.54

http://www.nutcracker.af...NSE.EQ.KEGN.O0000/quote[/quote]
Alot of shareholders re-alignment taking place in this counter going by the volumes being traded.


Maybe someone is throwing in the towel. Obviously, I believe its not PIC 😅
KaunganaDoDo
#167 Posted : Wednesday, September 18, 2019 1:47:26 PM
Rank: Member


Joined: 8/6/2018
Posts: 299
Ericsson wrote:
Kipevu I thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid


I don't think so. Kipevu 1 has a PPA until 2023. Olkaria V is has come in half, the other half in November 2019. One plant can not retire another one, they have separate tariffs, separate contracts. Early retirement is only possible if they pay off KenGen for the duration to PPA expiry
Extraterrestrial
#168 Posted : Wednesday, September 18, 2019 2:20:25 PM
Rank: Member


Joined: 11/17/2018
Posts: 173
Location: Mars
KaunganaDoDo wrote:
Ericsson wrote:
Kipevu I thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid


I don't think so. Kipevu 1 has a PPA until 2023. Olkaria V is has come in half, the other half in November 2019. One plant can not retire another one, they have separate tariffs, separate contracts. Early retirement is only possible if they pay off KenGen for the duration to PPA expiry


Iberafrica Power Plant's 56MW contract is set to end in October next year (this year), Tsavo Power’s (74MW) will end in September 2021, while Kipevu Diesel’s (60MW) contract runs up to July 2023.

https://www.businessdail...62918-kdaot5z/index.html
sparkly
#169 Posted : Wednesday, September 18, 2019 3:00:36 PM
Rank: Elder


Joined: 9/23/2009
Posts: 8,083
Location: Enk are Nyirobi
Extraterrestrial wrote:
KaunganaDoDo wrote:
[quote=Ericsson]Kipevu I thermal (73.5MW) to be retired once Olkaria V 162Mw is fully loaded to the grid


I don't think so. Kipevu 1 has a PPA until 2023. Olkaria V is has come in half, the other half in November 2019. One plant can not retire another one, they have separate tariffs, separate contracts. Early retirement is only possible if they pay off KenGen for the duration to PPA expiry


Iberafrica Power Plant's 56MW contract is set to end in October next year (this year), Tsavo Power’s (74MW) will end in September 2021, while Kipevu Diesel’s (60MW) contract runs up to July 2023.

https://www.businessdail...2918-kdaot5z/index.html[/quote]

The thermals at the coast might be kept for a bit longer. Transmission losses from Olkaria to Coast are very high.
Life is short. Live passionately.
Ericsson
#170 Posted : Wednesday, September 18, 2019 3:10:58 PM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
Extraterrestrial wrote:
Ericsson wrote:
[quote=Extraterrestrial]1,010,300 shares on Board at Sh5.54

http://www.nutcracker.af...NSE.EQ.KEGN.O0000/quote[/quote]
Alot of shareholders re-alignment taking place in this counter going by the volumes being traded.


Maybe someone is throwing in the towel. Obviously, I believe its not PIC 😅


Share price up by 26 cents to 5.80
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Ericsson
#171 Posted : Wednesday, September 18, 2019 11:27:17 PM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
Olkaria I Unit 6 is being constructed at a cost of $333 million (sh.34.6 billion)
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Ericsson
#172 Posted : Friday, September 20, 2019 4:40:41 PM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
Share price rallying ahead of release of FY results in October
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Ericsson
#173 Posted : Monday, September 30, 2019 9:56:09 AM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
Ericsson wrote:
Share price rallying ahead of release of FY results in October



https://pbs.twimg.com/me...ormat=jpg&name=large
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Ericsson
#174 Posted : Monday, September 30, 2019 11:56:37 AM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ach-full-load-operation/
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
KaunganaDoDo
#175 Posted : Monday, September 30, 2019 12:06:56 PM
Rank: Member


Joined: 8/6/2018
Posts: 299
[quote=Ericsson]As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ch-full-load-operation/[/quote]

This is premature reporting. I think commercial and capacity tests for unit one was completed last week...Unit 2 tests are yet to begin. Lastly, this plant doesn't yet have money allocated for it in the current electricity tariffs..
VituVingiSana
#176 Posted : Monday, September 30, 2019 12:32:13 PM
Rank: Chief


Joined: 1/3/2007
Posts: 18,103
Location: Nairobi
Marketer OiLibya, which is currently operating as Ola Energy, lost 8.5 million litres of fuel between 2012 and 2014 in a racket at the Nairobi terminal involving its own employees, Kenya Pipeline Company (KPC) staff and KenGen workers.
https://www.businessdail...92132-6fion6z/index.html
Greedy when others are fearful. Very fearful when others are greedy - to paraphrase Warren Buffett
Ericsson
#177 Posted : Tuesday, October 01, 2019 4:41:00 PM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
KaunganaDoDo wrote:
[quote=Ericsson]As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ch-full-load-operation/[/quote]

This is premature reporting. I think commercial and capacity tests for unit one was completed last week...Unit 2 tests are yet to begin. Lastly, this plant doesn't yet have money allocated for it in the current electricity tariffs..


https://kenyanwallstreet...ch-full-load-operation/

The Olkaria V plant has successfully reached the full load operation, injecting more than 160MW to the national grid.

The extraordinary milestone reinforces Kenya’s commitment to renewable energy sources and the reduction of carbon emission and global warming.

Kenya ranked third in renewable energy capital investments in the Middle East and Africa region in 2018. In the year, UNEP reports that Kenya attracted $1.4 billion (KSh145 billion) investments in renewable energy.

Furthermore, the Olkaria V unit 1 was synchronized into the national grid towards the end of July 2019. Kenya is among the top ten geothermal producing countries globally with an installed capacity of 612MW.
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Extraterrestrial
#178 Posted : Tuesday, October 01, 2019 6:33:06 PM
Rank: Member


Joined: 11/17/2018
Posts: 173
Location: Mars
Ericsson wrote:
KaunganaDoDo wrote:
[quote=Ericsson]As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ch-full-load-operation/[/quote]

This is premature reporting. I think commercial and capacity tests for unit one was completed last week...Unit 2 tests are yet to begin. Lastly, this plant doesn't yet have money allocated for it in the current electricity tariffs..


https://kenyanwallstreet...ch-full-load-operation/

The Olkaria V plant has successfully reached the full load operation, injecting more than 160MW to the national grid.

The extraordinary milestone reinforces Kenya’s commitment to renewable energy sources and the reduction of carbon emission and global warming.

Kenya ranked third in renewable energy capital investments in the Middle East and Africa region in 2018. In the year, UNEP reports that Kenya attracted $1.4 billion (KSh145 billion) investments in renewable energy.

Furthermore, the Olkaria V unit 1 was synchronized into the national grid towards the end of July 2019. Kenya is among the top ten geothermal producing countries globally with an installed capacity of 612MW.


Looks like a copy paste from the aforementioned.
KaunganaDoDo
#179 Posted : Tuesday, October 01, 2019 6:37:32 PM
Rank: Member


Joined: 8/6/2018
Posts: 299
Ericsson wrote:
KaunganaDoDo wrote:
[quote=Ericsson]As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ch-full-load-operation/[/quote]

This is premature reporting. I think commercial and capacity tests for unit one was completed last week...Unit 2 tests are yet to begin. Lastly, this plant doesn't yet have money allocated for it in the current electricity tariffs..


https://kenyanwallstreet...ch-full-load-operation/

The Olkaria V plant has successfully reached the full load operation, injecting more than 160MW to the national grid.

The extraordinary milestone reinforces Kenya’s commitment to renewable energy sources and the reduction of carbon emission and global warming.

Kenya ranked third in renewable energy capital investments in the Middle East and Africa region in 2018. In the year, UNEP reports that Kenya attracted $1.4 billion (KSh145 billion) investments in renewable energy.

Furthermore, the Olkaria V unit 1 was synchronized into the national grid towards the end of July 2019. Kenya is among the top ten geothermal producing countries globally with an installed capacity of 612MW.


This is all sensational reporting. The plant will reach longstop Full COD towards mid November...only 1'unit has been tested and commissioned. Each Unit is tested and commissioned separately,in sequence...before the plant as a whole is tested and commissioned....Anyway, When Olkaria V comes, it comes with costs...just like all beautiful girls, they come with High costs to the consumers
Ericsson
#180 Posted : Thursday, October 03, 2019 11:51:23 AM
Rank: Elder


Joined: 12/4/2009
Posts: 10,684
Location: NAIROBI
KaunganaDoDo wrote:
Ericsson wrote:
KaunganaDoDo wrote:
[quote=Ericsson]As KenGen's Olkaria V Unit 1 and 2 geothermal power plant has reached full load operation adding now about 160 MW in geothermal power generation capacity in Kenya.
With indications from various sources, it is now great to report that Olkaria V has successfully reached full load operations.

Units 1 and 2 are now injecting more than 160MW to the national grid. The capacity initially planned as 2×77 MW actually produces 2×85 MW.

We congratulate all involved in this great achievement. This achievement reinforces Kenya commitment with renewables and reduction of carbon emissions and global warming.

The Olkaria V geothermal plant, is one of the largest geothermal power plants currently under construction and the largest African geothermal plant.

The company reporting on the project, STEAM has been developing this project through its Kenyan company SGC to KenGen – Kenya Electricity Generating Company PLC. In this fascinating project STEAM has performed for Gathering and Power plant: Concept and Detailed Design, technical specifications & Bid Document Preparation and Pre-Qualification (PQ) documents preparation; Assistance in prequalification, bidding, bid evaluation, negotiations and Award processes for the EPC contractor; Supervision of the construction and commissioning ; Transfer of Knowledge.

http://www.thinkgeoenerg...ch-full-load-operation/[/quote]

This is premature reporting. I think commercial and capacity tests for unit one was completed last week...Unit 2 tests are yet to begin. Lastly, this plant doesn't yet have money allocated for it in the current electricity tariffs..


https://kenyanwallstreet...ch-full-load-operation/

The Olkaria V plant has successfully reached the full load operation, injecting more than 160MW to the national grid.

The extraordinary milestone reinforces Kenya’s commitment to renewable energy sources and the reduction of carbon emission and global warming.

Kenya ranked third in renewable energy capital investments in the Middle East and Africa region in 2018. In the year, UNEP reports that Kenya attracted $1.4 billion (KSh145 billion) investments in renewable energy.

Furthermore, the Olkaria V unit 1 was synchronized into the national grid towards the end of July 2019. Kenya is among the top ten geothermal producing countries globally with an installed capacity of 612MW.


This is all sensational reporting. The plant will reach longstop Full COD towards mid November...only 1'unit has been tested and commissioned. Each Unit is tested and commissioned separately,in sequence...before the plant as a whole is tested and commissioned....Anyway, When Olkaria V comes, it comes with costs...just like all beautiful girls, they come with High costs to the consumers



FY results to be out within the next two weeks
Wealth is built through a relatively simple equation
Wealth=Income + Investments - Lifestyle
Users browsing this topic
Guest (4)
35 Pages«<7891011>»
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.

Copyright © 2024 Wazua.co.ke. All Rights Reserved.