sitaki.kujulikana wrote:
sq and guest room 12 X 24 feet chini and the same juu.
Foundation;
Black cotton excavation 2.5 feet deep 4,000
Foundation stones 9' 11,500
Sand 13,500
ballast 10,000
Hardcore 6,000
Karatasi 800
Mabo 6X1 2000
Day 1
1 fundi, 2 kym, 10 bags cement foundation footings finished.
Day 2
1 Fundi 2 kym, 3 bags cement 1 foundation stone levels.
Rainned whole night the whole thing was flooded, water had to be removed first.
Day 3
1 Fundi, 2 kym, 3 foundation levels 8 bags cement
Day 4
Filling up with the hardcore
Day 5
1 fundi, 4 kym, 15 bags cement, foundation slab ika korogwa
Day 7
Structure,
Ndarugu mawe za 9, 600 feet(I think) 31,000
some mabati strip places between stone levels - around 1, 500
Prep work, 1 fundi, 2 kym 1 level stone work
Day 8
1 fundi, 2 kym, 3 levels stone work
Day 9
2 fundi, 2 kym, 3 levels stone work
Day 10
2 fundi, 2 kym 3 levels stone work
Day 11, 12, 13, 14
Hired trappers, mabo and poles 10,000
12 y12, 40 y10, 10 r8 binding wire kibao 35,000
2 fundi, 2 kym did the trappers and support and did the chuma work.
Day 15
Slab work 15,000
20 bags cement
sand 13,500
ballast 16,000
Thank you @SK, please keep them coming. Will put up mine too, in due process.
|