Rank: Elder Joined: 7/11/2012 Posts: 5,222
|
sitaki.kujulikana wrote: sq and guest room 12 X 24 feet chini and the same juu.
Foundation; Black cotton excavation 2.5 feet deep 4,000 Foundation stones 9' 11,500 Sand 13,500 ballast 10,000 Hardcore 6,000 Karatasi 800 Mabo 6X1 2000
Day 1 1 fundi, 2 kym, 10 bags cement foundation footings finished.
Day 2 1 Fundi 2 kym, 3 bags cement 1 foundation stone levels. Rainned whole night the whole thing was flooded, water had to be removed first.
Day 3 1 Fundi, 2 kym, 3 foundation levels 8 bags cement
Day 4 Filling up with the hardcore
Day 5 1 fundi, 4 kym, 15 bags cement, foundation slab ika korogwa
Day 7 Structure, Ndarugu mawe za 9, 600 feet(I think) 31,000 some mabati strip places between stone levels - around 1, 500 Prep work, 1 fundi, 2 kym 1 level stone work
Day 8 1 fundi, 2 kym, 3 levels stone work
Day 9 2 fundi, 2 kym, 3 levels stone work
Day 10 2 fundi, 2 kym 3 levels stone work
Day 11, 12, 13, 14 Hired trappers, mabo and poles 10,000 12 y12, 40 y10, 10 r8 binding wire kibao 35,000
2 fundi, 2 kym did the trappers and support and did the chuma work.
Day 15 Slab work 15,000 20 bags cement sand 13,500 ballast 16,000
Thank you @SK, please keep them coming. Will put up mine too, in due process.
|