4 bedroom house construction
Kaigangio
#11 Posted : Tuesday, December 30, 2008 12:40:00 PM
Rank: Elder

Joined: 2/27/2007
Posts: 2,768
then just give it an average of 25k per sq.m which works out to 8.1m for the total construction assuming that you will use average finishes and cheap electrical and plumbing fittings and accessories. The shorter the span of construction the better.

NEVER TALK OF A RHINO IF THERE IS NO TREE NEAREBY - ZULU PROVERB
...besides, the presence of a safe alone does not signify that there is money inside...
luttz
#12 Posted : Tuesday, December 30, 2008 2:07:00 PM
Rank: Member

Joined: 3/18/2008
Posts: 377
Boss!

Thank you so much

Can you please get in touch with me on luttah@yahoo.com or lutalala@un.org

Your advise appreciated.

Luttz
"You've never lived until you've almost died; for those who have fought for it, life has a flavour the protected will never know."
simonkabz
#13 Posted : Wednesday, December 31, 2008 5:30:00 AM
Rank: Elder

Joined: 3/2/2007
Posts: 8,776
Location: Cameroon
@ luttz,is ua other name polycarp? Just curious,u sound lyk a dude i knw,fm MHS

You never know what u can get away with until u try it!
TULIA.........UFUNZWE!
Obi 1 Kanobi
#14 Posted : Thursday, February 05, 2009 11:39:00 PM
Rank: Elder

Joined: 7/23/2008
Posts: 3,017
Hi good people,

Can someone give me a breakdown of the process of putting up a 3 bedroomed house,simple thing.

I know its a big ask but I am sure there's a contractor somewhere here with a bit of time to burn.

Kindly post the process from A-Z with material and labour needs for a standard hse with decent (not expensive) finishing.


I guess if you can't win with facts,you can always pen bile-laced,xenophobic rants to distract everyone.
"The purpose of bureaucracy is to compensate for incompetence and lack of discipline." James Collins
Djagame
#15 Posted : Friday, February 06, 2009 8:52:00 AM
Rank: Member

Joined: 12/10/2008
Posts: 68
Location: Nairobi
@obi 1 kanobi

Ideal process is a s follows:


Identify an architect (lead consultant)
Come up with a design brief (You and architect)
Site visit by architect - important as site features may determine/influence overall design
Come up with design upon consultation and input from both parties
Approve design after which architect picks other conultants (Engineers,surveyors,contractors etc)
Quantity surveyor produces bill of quantities (gives cost estimate of construction according to design) after input from consultants
After your assent of the above the drawings are taken for approval to city/county council
Once approved architect sends contractor to site to commence construction. (You may choose to work with your own contractor)
During construction architect to pay site visits to ensure construction being carried out according to plan or make necessary changes
Upon completion of construction city/council officers to approve - rarely happens
E & O. E.

To help you out in budgeting cost estimates for residential construction ranges from KShs 25,000.00-KShs 32,000.00 per square metre depending on the finishes.

You can do away with some of the above but absolute musts are pick an architect to do the design and also get your design approved.

Hope this helps and for more details send a mail to info@modelsandrenders.com



'Whatever can go wrong will go wrong,and at the worst possible time,in the worst possible way.' - Murphy

"We do not inherit the earth from our ancestors, we borrow it from our children" Native American Proverb
Gems
#16 Posted : Friday, February 06, 2009 9:45:00 PM
Rank: Member

Joined: 4/16/2008
Posts: 16
Location: California. US
Does anyone have estimates on the architectural both physical and structural. my plan is to construct a 2-4storey building for univ student hostel or apartments 1 and 2 bedrooms. I have plots at Annex campus of Moi univ,Eldoret. Do you know any Credible constructors that you guys have worked with. Any advise from people who are experienced in this? Its my very first project and as a lady,am afraid people will take advantage and overcharge me. Any helpful info will be appreciated

Gems
Obi 1 Kanobi
#17 Posted : Saturday, February 07, 2009 12:54:00 AM
Rank: Elder

Joined: 7/23/2008
Posts: 3,017
Thanks Djagame

Will email with more defnite questions.


I guess if you can't win with facts,you can always pen bile-laced,xenophobic rants to distract everyone.
"The purpose of bureaucracy is to compensate for incompetence and lack of discipline." James Collins
achy
#18 Posted : Saturday, February 07, 2009 12:28:00 PM
Rank: Member

Joined: 12/9/2007
Posts: 7
@ Gem,

kindly get in touch isaiahkiburi@yahoo.com,Can get u some valuable tips.


Not the best,but not like the rest.
Gideonboots
#19 Posted : Sunday, February 08, 2009 4:21:00 PM
Rank: Member

Joined: 12/27/2006
Posts: 17
@ achy

kindly give estimates as asked by Gem,so that we all benefit.

But for finer details she can email you.

Thanks guys


Hand that Giveth Receiveth
Gems
#20 Posted : Sunday, February 08, 2009 9:04:00 PM
Rank: Member

Joined: 4/16/2008
Posts: 16
Location: California. US
@achy,
I will email you asap.
thanks everyone,i have learned a thing or two

Gems
4 Pages<1234>
Forum Jump  
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.

Copyright © 2026 Wazua.co.ke. All Rights Reserved.